Monday Consulting Questions: Scope Creep and Getting Paid

By Christopher Hawkins •  Updated: 08/28/06 •  5 min read

Today I’m just going to tackle one Consulting Question.

Q. I need to negotiate payment on a project that went out of scope. How do I do this?

A. Trying to get paid for out-of-scope work after it’s been done can often be like trying to un-ring a bell. Depending upon the circumstances, it may not even be possible to get that scope creep paid for. So, let’s look at the circumstances.

The first thing to think about is, how do we know this project went out of scope? Do we have a measurable way to determine what features comprise the project’s scope, like a functional spec? If not, you have a real problem, because without some record of what the project’s expectations were at the start, anyone can interpret anything however they want. To be honest with you, if you don’t have anything to prove that the project is out of scope, you’re sunk. Start negotiating and be happy to get whatever you can get.

Now, if you do have a scope document, you’re on more solid ground. However, you’re not out of the woods just yet. Did you set the client’s expectations correctly? That is, did you either:

a) notify the client at the outset that additional features would increase the cost, or
b) notify the client at the time of the change request that the change would increase the cost?

Yes, I know your client is staffed by adults and that adults have no excuse for thinking that more work costs nothing extra, but to be perfectly honest, nobody cares about you or whether or not you are treated fairly. It’s sad but true:

You get what you negotiate. Nobody will be fair with you; you have to defend yourself at all times.

So, if your client can throw up the “but you didn’t TELL me this would cost extra” defense, you’re in a tough position with regard to scope creep once you let it happen. At best, you can point to the scope doc and offer to remove the additional features if they don’t want to pay for more then the original scope. But in all honesty, the moment a client plays the “but you didn’t tell me” card, you’re sunk.

The third scenario — the one that puts you in the best position — is that you have both a scope document and you have communicated effectively with the client. The scope documentation proves what you were setting out to build, which means that anything not in that document doesn’t exist. So, changes are easy to identify and scope creep is easy to illustrate. The communication ensures that at the very start of the project OR at the moment a change request came in, the client was informed that yes, when you request more work, you have to actually PAY for it.

This is a one-two combo that even the most dishonest of clients will have a hard time applying twisted “you should work for free” logic to.

Here’s how I manage scope creep at Cogeian Systems:

I don’t necessarily think that scope creep must be avoided. It CAN be avoided, but I don’t think it MUST be in every case; sometimes scope creep is a good thing for a project — it can be a sign of opportunity for the client, and a chance to (ethically!) up-sell for you as a consultant. However, there is no question that scope creep must be managed. The client must have an opportunity to think about the consequences of change in terms of additional cost, longer delivery time, additional complexity, etc. And the developer must be paid for the work provided.

So, the short answer is, you get paid for out-of-scope projects by defining a change process before the work ever begins. Barring that, it’s up to you and your negotiation skills. Try to do better next time.

Do Your Clients Ever Make You Furious?

If so, I offer a free 10-day e-mail course that can help you resolve exactly the kind of conflict that’s outlined in the article above.  Paying late, not responding to emails, arguing about art direction…enough is enough.  Sign up for Conquering Client Conflict today and learn to make more money & get more respect by squashing these conflicts.